City of Tempe, AZ
Home MenuScottsdale Road Bike Lane Project
Construction to improve pedestrian and bicycle accessibility on Scottsdale Road from Continental Drive (Roosevelt Street) to Curry Road is underway. Project improvements include buffered bike lanes, pedestrian curb ramps and pedestrian push buttons. The project will be constructed in multiple phases and is anticipated to be completed in summer 2026. Once complete, the existing number of traffic lanes and medians will be maintained. Crews are currently working on the west and east sides of Scottsdale Road from Curry Road to Continental Drive (Roosevelt Street).
Construction Updates
Starting on June 8, crews will be working on Scottsdale Road from Curry Road to Continental Drive (Roosevelt Street), making utility adjustments, installing a pedestrian fence in the center median, north of Hancock Avenue, finishing electrical installations and installing and installing temporary striping for the project. Work hours will be 5 a.m. to 5 p.m., 4 a.m. for concrete pouring. Final project completion is anticipated in August 2026. The Orbit Earth route will be detoured, for latest information: valleymetro.org/rider-alerts. Tempe will work to minimize impacts during this project.
Impacts:
• Southbound and northbound traffic lanes along Scottsdale Road will be restricted to one lane in each direction from 5 a.m. – 9 p.m. until work is completed
• If the utility adjustment activities cross driveways and side streets, there may be a period of time where access is restricted; however, crews will work to expedite this activity and restore access as quickly as possible
Please follow no parking signage when posted. Pedestrian, business and residential access will be maintained. Project timelines and hours are subject to change due to unforeseen circumstances.
Roosevelt Storm Drain Project
Starting April 13, there will be additional intermittent traffic and turning lane restrictions along Scottsdale Road starting at the Continental Drive (Roosevelt Street) and Scottsdale Road intersection for the Roosevelt Street Storm Drain Project until June. Traffic control will remain in place 24/7. For more information about this project tempe.gov/waterprojects
Project Hotline: 480-898-4100
Funding
Tempe received a grant from the Maricopa Association of Government’s Transportation Alternatives/Congestion Mitigation and Air Quality (CMAQ) Program in the amount of $5.9 million; an additional $356,665 in local funds will go toward the completion of the project.
Public Meetings
- Feb. 17 and 19, 2022, and online comment was taken Feb. 17 to March 6, 2022.
- Nov. 3 and 6, 2021, and online comment was taken from Nov. 3 to 17, 2021.
- August 18, 2025
Contact: Chase Walman, 480-858-2072, chase_walman@tempe.gov
Documents
- August 2025 Construction Public Meeting Board 1 PDF
- August 2025 Construction Public Meeting Board 2 PDF
- February 2022 Public Meeting Presentation PDF
- February 2022 Cross Section Alternatives PDF
- February 2022 Three Foot Buffer Alternative PDF
- February 2022 Two Foot Buffer Alternative PDF
- February 2022 Public Comment PDF
- November 2021 Public Comment PDF
- November 2021 Public Meeting Presentation PDF
- November 2021 Aerial of Scottsdale Road Bike Lane Improvements PDF