Join us on Nov. 2, 2019  from 9 to 10 a.m. to celebrate the opening of the path.  A small event will take place on the portion of the path located north of Auto Drive. 

The purpose of the project is to design and construct a 10-foot wide concrete multi-use path with lighting, landscaping and public art. The project includes street crossing treatments and possible bicycle/pedestrian bridges across the canal. The project is located along the Tempe portion of the Highline Canal and links directly to Chandler and the Town of Guadalupe for a distance of 3.5 miles. Map of project area PDF.

Construction Funding:

  • $3.2 million Transportation Alternatives Federal grant
  • $65,000 Congestion Mitigation and Air Quality Improvement grant
  • $200,000 Transit Tax

Public Involvement:

A public meeting about the proposed artwork was held Sept. 11, 2017. Comments were taken online about the art concepts from Sept. 11 to Sept. 24, 2017. View the Art Concepts.pdf. Read the comments from the public meeting in Sept. 2017 PDF.

A public meeting was held March 14, 2017 and online comment was available March 14 to March 28, 2017. Read the comments PDF.

A public meeting occurred on Aug. 31, 2016. Online public comment was available Aug. 31 to Sept. 14, 2016. View the comments here PDF.

For more information, contact Project Manager,  Chase Walman, at 480-858-2072.