Highline Canal Multi-use Path

Print
Press Enter to show all options, press Tab go to next option

 

The Highline Canal Multi-use Path is identified in the Comprehensive Transportation Plan and the Tempe 2030 and 2040 General plans. The purpose of the project is to design and construct a 10-foot wide concrete multi-use path with lighting, landscaping and public art. The project includes street crossing treatments and possible bicycle/pedestrian bridges across the canal. The project is located along the Tempe portion of the Highline Canal and links directly to Chandler and the Town of Guadalupe for a distance of 3.5 miles. Map of project area.

Construction Funding:

  • $3.2 million Transportation Alternatives Federal grant
  • $65,000 Congestion Mitigation and Air Quality Improvement grant
  • $200,000 Transit Tax

Timeline: 

  • Construction is underway                             
  • Anticipated completion date: January 2019.

Public Involvement:

A public meeting about the proposed artwork was held Sept. 11, 2017. Comments were taken online about the art concepts from Sept. 11 to Sept. 24, 2017. View the Art Concepts. Read the comments from the public meeting in Sept. 2017. 

A public meeting was held March 14, 2017 and online comment was available March 14 to March 28, 2017. Read the comments.

March 14, 2017 Project PowerPoint & Design Concepts

March 14, 2017 Public Meeting Materials

 

Below are pictures of the existing conditions.

Highline Canal  Highline Pic 2

Highline Pic 3  Highline Pic 2

 

PowerPoint presentation from October 2014 

August 2016 Design Concepts

A public meeting occurred on Aug. 31, 2016. Online public comment was available Aug. 31 to Sept. 14, 2016. View the comments here. 

For more information, contact Project Manager, Robert Yabes, at 480-350-2734.