APPLICATION INSTRUCTIONS:
- Customer fills out the application, including a map of the route.
- Customer submits completed application to Traffic Engineering for review and approval. (Traffic Engineering will review within 48 hours.) Application can be submitted via fax
(480-350-8878); e-mail (trafficbarricade@tempe.gov); by mail at P.O. Box 5002, Tempe, AZ, 85280; or visit the office at 200 E. Fifth Street.
- Once approved, Traffic Engineering forwards completed application to Engineering.
- Engineering ensures that customer’s Insurance Certificate, Contractor’s License, and Privilege Tax Number are on file and current. (Engineering will review within 24 hours.)
- Engineering assigns a Permit #, collects fees (if applicable), and issues Hauling Permit.
- For Over-size/Over-weight permits click here.
DEFINITIONS:
Dates of Hauling Operation: Start date - Finish date.
Number of Days of Operation: Total number of calendar days (start to finish).
On-Site Work Hours: Hours being worked by general contractor.
Times of Haul: Hours of haul operations.
No haul allowed during peak hours (7:00-8:30AM, 4:00-6:00PM).
Night hauling requires Noise Abatement Permit.
Number of Trucks: Example: One every 3 minutes equal 20 trucks (60 min cycle)
Frequency of Truck Circulation: Example: One every 3 minutes.
Type of Truck: Check appropriate box.
Total Cubic Yards of Haul: Self-explanatory.
Street Names/Routes to be used: Attach a map showing export site, import site, and route.
No hauling through construction sites.
NOTES ON CHANGING APPROVED HAUL ROUTE PERMIT; FEES:
New Import Site: Requires NEW Haul Permit Application with updated map showing “original” import site, “new” import site, and route.
(Note: Same Haul Permit Number; No New Fees.)
New Export Site: Requires NEW Haul Permit Application with updated map showing “original” export site, “new” export site, and route.
(Note: New Haul Permit Number; New Fees Assessed.)
Fees: Under 5,000 cubic yards and less than 10 calendar days in duration..............No charge
Under 5,000 cubic yards and more than 10 calendar days in duration.....................$552.40
5,000 to 10,000 cubic yards................................................................................$552.40
Greater than 10,000 cubic yards.........................................................................$2,209.55
Fees subject to change.