TARGET TURN AROUND TIMES  Time Frames for Approval or Denial (SS 9-835)
Type of Plan Review   Initial Plan Review
Working Days 
 Re-submittals
Working Days
Administrative
Completeness
Calendar Days 
 Substantive
Review
Calendar Days
Overall
Time
Calendar Days 
 New Commercial -
 > $10 million valuation
 Negotiated > 20  >10  15  300  315
 New Commercial -
 < or = $10 million valuation
 20  10   15   200  215
 Additions/Alterations
(time dependent upon scope of work)
 15-20  8-10   15   65  80
 Tenant Improvements
 > $500,000
 12  8  10  45  55
 Tenant Improvements
 < $500,000
 8  6  10  35  45
 Other  8  6  10  35  45
 AFES  8  4  10  35  45
 MEP only  8  4  10  35  45
 Residential  8  6  10  35  45
 Fire  6  4  10  35  45
 Revisions  4  4  10  25  35
 Engineering
 (single family subdivision/
commercial / multifamily)
 15  1st re-submittal: 10 days
 All subsequent re-submittals:
5 days
 < 5 acres: 15
> 5 to 15 acres: 20
> 15 acres: 30
 < 5 acres: 35
> 5 to 15 acres: 70
> 15 acres: 110
 < 5 acres: 50
> 5 to 15 acres: 90
> 15 acres: 140
 Engineering
(single family residence)
 10  8  10  30  40

Please note: These are target turn around times only and may change due to
workload, staffing considerations, and size or complexity of project. 
We meet our target turn around times on more than 98% of all reviews.