| TARGET TURN AROUND TIMES |
Time Frames for Approval or Denial (SS 9-835)
|
| Type of Plan Review |
Initial Plan Review
Working Days |
Re-submittals
Working Days |
Administrative
Completeness
Calendar Days |
Substantive
Review
Calendar Days |
Overall
Time
Calendar Days |
New Commercial -
> $10 million valuation |
Negotiated > 20 |
>10 |
15 |
300 |
315 |
New Commercial -
< or = $10 million valuation |
20 |
10 |
15 |
200 |
215 |
Additions/Alterations
(time dependent upon scope of work) |
15-20 |
8-10 |
15 |
65 |
80 |
Tenant Improvements
> $500,000 |
12 |
8 |
10 |
45 |
55 |
Tenant Improvements
< $500,000 |
8 |
6 |
10 |
35 |
45 |
| Other |
8 |
6 |
10 |
35 |
45 |
| AFES |
8 |
4 |
10 |
35 |
45 |
| MEP only |
8 |
4 |
10 |
35 |
45 |
| Residential |
8 |
6 |
10 |
35 |
45 |
| Fire |
6 |
4 |
10 |
35 |
45 |
| Revisions |
4 |
4 |
10 |
25 |
35 |
Engineering
(single family subdivision/
commercial / multifamily) |
15 |
1st re-submittal: 10 days
All subsequent re-submittals:
5 days |
< 5 acres: 15
> 5 to 15 acres: 20
> 15 acres: 30 |
< 5 acres: 35
> 5 to 15 acres: 70
> 15 acres: 110 |
< 5 acres: 50
> 5 to 15 acres: 90
> 15 acres: 140 |
Engineering
(single family residence) |
10 |
8 |
10 |
30 |
40 |
Please note: These are target turn around times only and may change due to
workload, staffing considerations, and size or complexity of project.
We meet our target turn around times on more than 98% of all reviews.