|
NEWS
|
DATE |
ARTICLE / SUBJECT |
|
MARCH 2007 |
Hayden Flour
Mill Archaeology Update
For information, please contact Victoria Vargas at
480.894.5477 or
Susan Shaffer Nahmias at 480.496.0978.
|
|
for week ending
21 JULY 2006 |
Our final day in the field for the testing phase was Monday, July
17, 2006. Our final tasks included completing the last trench wall
profile maps on the north side of the mill building, final
photographs of the trenches and the features they contained
(possible prehistoric canals and the substantial rock retaining wall
lining the west side of the Hayden Canal), and collecting final shot
data of the units, features, and property contours. After completing
these tasks, the open units were backfilled. We are now busy
reviewing data collection forms and other field data in anticipation
of data entry and map production tasks in the weeks ahead.
The field principal investigator and supervisors
will begin the task next week of reviewing each feature and
assessing its significance to the history of the site, followed by
determining if data recovery is advisable for any of them. For
example, we know that many features identified during testing will
require some level of data recovery, including the gas station,
calaboose, and the features on the north side of the building, but
we may find that we’ve recovered the important data for others, such
as the prehistoric canals, railroad, and earthen portion of the
Hayden Canal.
When the data entry tasks are completed in the
next few weeks, we can run queries for number of artifacts
collected, features investigated, units excavated, square meters of
trenching, and cubic meters of earth removed.
It will be a number of weeks before the next stage of the
archaeological dig begins.
|
|
AUGUST 2006
|
PHOENIX MAGAZINE
The Phoenix Files - The Flour Mill's Future
|
|
for week ending
14 JULY 2006
|
The last of our exploratory trenches went in on the north and west sides
of the mill building, in addition to explorations in the dirt parking
lots on the northeast side of the property above Rio Salado Parkway. Our
trenching in the parking lot areas revealed no subsurface cultural
deposits or features, only naturally occurring slopewash and alluvial
(rock) accumulations in the drainage channels. In the upper dirt lot
nearest the large circular concrete pads, we found large chunks of loose
bedrock that could be waste materials from quarrying that was necessary
to level the surface for the pads. There were no signs of prehistoric
occupation or use in either area nor did we encounter any archaeological
remains of the historic carpenter’s shop or blacksmith’s shop. This is
likely due to the high level of previous disturbance in both areas.
Excavations on the west side of the mill building
revealed no historic features below the 1920s warehouse foundations.
However, we did find two small canal alignments. These appear to be
prehistoric, but with few associated artifacts—which consisted of both
prehistoric and historic items—and no burned material suitable for
radiocarbon dating, the dating remains uncertain. A review of historic
photographs may be of value; no photographs seen thus far of the west
side of the original mill building show a canal(s).
On the north side of the mill building, our deep
east-west trench between the building and the historic concrete pads
found earlier, uncovered a massively built dressed stone wall, the top
of which was approximately 1 ft beneath the surface. The deep fill on
the east side of the wall is dark and full of late 19th to
early 20th century artifacts, including bottles and metal
items. The deep central part of the exploratory trench went down 8–9 ft
on both sides of the wall and its base was not yet encountered. The west
side of the wall contained a builder’s trench in natural stratigraphy.
Clearly, the east side of the wall is the main Hayden Canal below the
water wheel, and the deep cut in natural stratigraphy found late last
week in our north-south trench just to the east must be where the waste
race rejoined the main canal. We suspect that the waste race stone arch
and other potential walls are still buried below our 8–9 ft excavation
level. Why there is such a tall, massively-built wall lining the west
side of the main canal is still a mystery at this point, but hopefully
will be investigated further in the next phase of work.
While extending the deep east-west trench further to
the west beyond the stone wall, we encountered two large canals that
appear to be prehistoric. This finding is not surprising, given that we
picked up two canals along the west side of the property, and in Volume
2 of The Lost Itinerary of Frank Hamilton Cushing indicates that
Charles T. Hayden told Cushing that he encountered prehistoric canals on
the property when they were excavating the race for the mill. Hayden
mentioned that he had uncovered “considerable lengths of an ancient
irrigating canal and from this canal other and lesser acequias were
found to branch off.”
Other areas that were investigated include closing
out the final hand-excavated unit south of the temporary fence where the
earthen Hayden Canal was encountered, and taking out the last of the
recent fill at the northernmost bay along the east side of the mill
building. A slim concrete foundation was found beneath the fill in the
bay, but its function remains unknown at this point.
|
for week ending
7 JULY 2006 |
Archaeology work continues on the Hayden Flour Mill.
A display has been set up inside the lobby at Monti's La Casa Vieja to
help describe the project.
No prehistoric remains were encountered, even though
we concentrated units near the Light Rail portion of the project area.
In the northernmost hand unit between the railroad and the parking lot,
we encountered deep silty deposits, quite unlike the fill and bedrock
exposed in the other units. We extended a narrow hand trench to the east
and encountered a cut in bedrock. At first we thought this might be a
prehistoric pithouse, but further exploration revealed that it was
likely the Hayden Canal. This was somewhat surprising as it is slightly
offset from the alignment formed by the other exposures. Because of this
“irregularity” in the alignment, we will excavate a narrow hand trench
to the west on Monday to try to catch the rest of the canal, and will
place another hand trench between this unit and the southern temporary
fence to catch the canal there as well. With these results and the
exposures in the fenced area, we will be able to accurately plot the
exact alignment of the canal across the property.
Trenching work continued on the north side of the mill building
around the historic concrete pads uncovered late last week. In the
northernmost east-west trench along Rio Salado Parkway, we
encountered an area of fill roughly in alignment with the Hayden
Canal main race, but have not confirmed this assessment yet. At the
western end of this trench, near the corner of Rio Salado and Mill
Avenue, we encountered two prehistoric canals. They appear to be
feeder canals or laterals; neither is large. The north-south trench
between these canals and the 1920s warehouse foundation, we
uncovered several concrete slabs and areas of disturbance (broken
concrete dumped in a large “hole” and other vertical cuts in the
natural stratigraphy). At the southwest corner of the mill building,
we expanded a trench to uncover the northern portion of the
suspected calaboose. We discovered two concrete slabs with a layer
of brick and shaped stone beneath. Although the western portion
appears to have been disturbed, we are beginning to get a sense of
how large the structure is and its orientation. At the southeastern
corner of the mill building, we placed another trench that uncovered
the concrete “tunnel” for the Hayden Canal and a later concrete slab
partly above it and to the east. A remnant of the original earthen
canal appeared to be under the slab, which had been filled with
debris and sediment. Lastly, we uncovered the concrete tunnel and
another concrete foundation to its east at the northeast corner of
the mill building. We have not completed fill removal, so we cannot
tell if the foundation is part of the waste race. It is possible
that it is a remnant of the original mill building. It also seems
that the water “dropped” in this area and that the milling equipment
must be in the building beneath this point.
[photogallery/photo00027226/real.htm] |
|
for week ending
30 JUNE 2006 |
This was the first week of archaeological testing fieldwork.
The majority of ACS activity this week was in support of the field
effort.
No Hayden Flour Mill Committee meeting was held this
week.
The next meeting will be held at 4 pm, July 10, 2006 at the City of
Tempe Community Development Offices.
ARCHAEOLOGY
Testing began on schedule at the project area, and we’ve
already completed a major portion of the backhoe and hand unit tasks
within and adjacent to the mill buildings. We’ve excavated 13 trenches
and 7 hand units, and made several interesting discoveries thus far. In
the lower parking lot area adjacent to Mill Avenue, we’ve uncovered the
concrete foundations of what appears to be the 1920s–1940s gas station,
and the Hayden Canal beneath the concrete slurry covering at the lot’s
eastern end. The canal in this area appears to be earthen; the covering
of concrete slurry along the canal route appears to be more recent,
perhaps to stabilize the slope. The earthen canal appears to be fairly
wide and shallow in this area, and has a silty-clay sediment.
In the mill complex itself (inside the permanent fence),
we uncovered a concrete canal culvert, which in fact may be a completely
encased concrete “tunnel” for the main canal leading towards the mill
grinding equipment. Another concrete slab covering the canal was found
beneath the recent fill adjacent to the east side of the mill building.
We excavated a trench from the concrete covering eastwards toward the
rail line and uncovered the waste race. Like the main canal (mill race),
it is encased in concrete, except that it does not have a concrete
covering. Its trajectory away from the main canal matches archival map
depictions of the waste race. With its trajectory now known, we can
extrapolate to the south and possibly pinpoint where the waste race
diverged from the main canal. During data recovery, we can open up this
area, where we will likely find a headgate for diverting water into the
waste race.
We also placed four short east-west trenches between the
mill building/rail line and the silos. A moderately thick lens of burned
material composed of dark ash and cinder/slag was found covering a large
area. Although we at first thought this may represent a fire, it seems
more likely that it was burned refuse from the train engine purposefully
laid down around the tracks to retard vegetation growth and diminish the
chance of fire from engine sparks.
Near the southwestern corner of the permanent fence, we
uncovered what appeared to be the remains of the calaboose. We have a
nice stone foundation remnant on the north side of the trench and a
brick sidewalk, walkway, or floor on the south side of the trench at
this location. The western half has been severely impacted by later
construction. We began a cross trench across the feature to document its
dimensions and to see how this compares with the estimated size of the
calaboose. We immediately encountered a concrete slab remnant and a
layer of busted brick and mortar, along with some architectural rock and
an old asphalt lens. We will know more once we complete the cross trench
on Monday, July 3, 2006.
Just north of the calaboose feature, we excavated a
north-south oriented trench to the 1920s concrete slab remnant. Several
old pipes were found, which may be SRP related, and a canal-like feature
with cobbles along its sides. However, our geomorphologist examined this
feature and concluded that it is more likely a builder’s trench or
related feature associated with the 1920s structure. No prehistoric
artifacts have been found thus far.
On the north side of the mill building, we’ve uncovered
another large concrete slab beneath the fill that was under the loading
dock slab (which we removed prior to testing). We were expecting to find
structure foundations, but may have actually uncovered the floor(s) of
the structure(s) that was left intact. Because this is large and we
cannot break through the concrete, our remaining trenches will need to
be relocated along the edges of the slab where dirt fill occurs. This
strategy will still allow us to explore beneath the level of the new
slab feature in our search for the earliest remains of the mill. In
fact, placing a long east-west trench between the current mill building
and the newly discovered concrete slab will cross the Hayden Canal
outflow channel—we may pick up evidence for this while conducting deep
trenching.
Our final trench excavated thus far was along the north
side of the large round concrete slab, which revealed only modern fill
to bedrock; no traces of the early blacksmith or carpenter’s shops were
found.
The hand units along the railroad tracks and along the
butte slope south of the mill buildings revealed that bedrock is
generally shallow in this area. In several units adjacent to the tracks,
we again picked up dark ash and cinders/slag, which appears to be
typical railroad bed materials. In a unit closer to the concrete slurry
over what we thought was the Hayden Canal, we encountered a fairly deep
deposit of silts then clays, which appears to be canal deposits. We will
put in a hand trench to see if we can verify that this is the earthen
Hayden Canal; this is scheduled for Monday. No prehistoric remains or
artifacts have been found so far in this area.
Visitors this week include Teresa Pinter (ACS
preservation plan PI) and Susan Shafer Nahmias (ACS public outreach PI)
on Thursday, and Joe Nucci and Chris Messer on Wednesday afternoon and
Friday morning. To date, we have not been contacted by any media
outlets, nor have any casual or inquisitive visitors stopped by to ask
questions. The Tempe police stopped by on Wednesday to ask about our
vehicles in the northern dirt lot; we explained again about our bright
yellow parking passes, which we are placing on dashboards in plain
sight. Next week promises to be just as exciting as the first. As a
reminder, we will not be working on the holiday, July 4 (Tuesday). The
areas that the fire department identified as their staging zones are
completely available to them.
ARCHIVAL RESEARCH
Victoria Vargas delivered Bill Mitchell’s Hayden Flour
Mill slides to Richard Bauer at the Tempe Historical Museum for
duplication. The Museum will scan the ca. 1980 slides and provide ACS a
copy of the images on a CD or DVD.
Victoria continued compiling and reviewing archival
materials and worked on historic context development.
Historic
Architecture
Victoria Vargas and Don Ryden met on Wednesday, June 28,
2006 and completed negotiations of Ryden Architects’ Scope of Work and
budget for the Hayden Flour Mill project. A copy of that scope and
budget was submitted to Margerie Green, ACS President and Owner, for her
approval. Once approved by Margerie Green, it will be submitted to the
Hayden Flour Mill Committee for their approval.
Historic
Preservation Plan
No activity on the HPP this week.
Educational +
Public Outreach
The electronic files for the Monti's La Casa Vieja
exhibit were delivered to Eric Hansen at COT on Wednesday, June 28. The
printed panels will be available from COT on Monday, July 3 and will
need to be laminated prior to display. We anticipate the exhibit will be
installed at Monti's late next week or early the following week, subject
to their schedule.
|
|
15 JUNE 2006 |
The
City of Tempe approved an agreement to settle the litigation on the
Hayden Flour Mill on June 15. The major terms of the development
agreement include:
·
MCW will purchase the Flour Mill
property from the City for $7.4 million. The City shall credit MCW $7.1
million for public amenities to be constructed as part of the project,
but only at such time as
MCW is ready to pull
construction permits. Such public amenities include a reconstructed
trail head with parking for Hayden
Butte, traffic signalization and infrastructure,
publicly-accessible exhibits and displays outlining the prehistoric and
modern history of the site, as well as preservation easements in favor
of the City on the Mill and Silos.
·
The City will provide $6 million [net
present value] in additional payments to offset the extraordinary costs
of the preservation and restoration of the Mill and Silos.
·
The Flour Mill property will be
entitled to 469,160 square feet of development [the same as allowed for
in the previous development agreement]. The Hayden Ferry South
Development Guidelines approved
by the Rio Salado Advisory Commission in May 2000 shall be used to guide
development on this site except for subsection D relating to building
heights and massing. All building heights on the Flour Mill site shall
be limited to the height of the Silos or 168 feet.
·
The ultimate project on the Flour Mill
site is intended to be a mixed use development including retail along
Mill Avenue, office, residential [amount and unit type to be
determined], and potential for a
boutique hotel.
-
MCW
reserves the right to assign all or part of the Development and
Disposition Agreement.
-
MCW, or
its Assignee, shall perform under specified time deadlines.
|
|
for week ending
23 JUNE 2006 |
ARCHAEOLOGY
Work with the
backhoe began Monday
morning; Staff inspected
the fill uncovered beneath the concrete slabs near
Rio Salado Parkway to see if they could
use their 4-foot grader blade without damaging anything
or hitting large rocks. Staff
will strip some of the loose fill off of the
planned trench locations in this area so that we can reach the
natural or original ground surface. A site walkover was done on 20 June to ground truth the placement of hand excavation test
units.[photogallery/photo00010392/real.htm]
|
|
for week ending
9 JUNE 2006 |
Hayden
Flour Mill Testing Project
ACS Weekly Progress Report
The majority of effort this week was dedicated to
prefield tasks for the upcoming archaeological fieldwork, preparing and
giving the public presentation at the Tempe Historical Museum [8 June],
and continuing development of the Monti’s exhibit.
ARCHAEOLOGY
As reported last week, The concrete removal was completed
at the end of May. Some prefield logistical tasks were begun this week,
which will intensify next week, including preparing field paperwork,
conducting a pre-field logistical meeting of the archaeology component
supervisors,
preparing the database for data entry, etc.
ARCHIVAL RESEARCH
Victoria Vargas continued research into the Hayden Family
context study. She also put together a detailed outline of the testing
report, identifying how each of the component’s results will be
presented in relation to each other and how they will be synthesized
into a single interpretive chapter. Introductory sections of the report
are currently being composed.
On 8 June, the team presented the kickoff PowerPoint
presentation to a large audience assembled at the Tempe Historical
Museum building, hosted by Dr. Amy Douglass. Work is being done on an
exhibit for Monti’s La Casa Vieja on this project. The exhibit will be
put up before the end of June.
|
|
8 JUNE 2006
|
The Business Journal
Hayden Flour Mill Moves Toward Rebirth |
|
3 JUNE 2006
|
AZ Republic
Milling Grains of History
|
|
event date
8 June 2006 |
Learn About Hayden Flour Mill Archaeology
Those interested in the archaeology
of the Hayden Flour Mill can learn about it next Thursday night.
Archaeological Consulting Services, Ltd. [ACS]
will present an overview about the current Hayden Flour Mill
Archaeological and Historic Architecture Testing project at 7 p.m.
on 8 June at the Tempe Historical Museum, 809 E. Southern Ave.
[SW corner of Southern Avenue + Rural Road].
The City of Tempe, with funding from the Salt
River Pima and Maricopa Indian Community, is sponsoring the testing
project to further preservation efforts of the Hayden Flour Mill
buildings, while preparing for future redevelopment of the property.
This project is the first stage in that process.
ACS staff will discuss goals, present an
explanation of the different components of the project, which
include archaeology, historic architecture, archival research and a
historic preservation plan.
ACS also will present a schedule of the coming archaeological
fieldwork and overall project. There will be time for a question and
answer session at the end of the presentation.
Call Dr. Amy
Douglass at 480.350.5100
for more information.
|
|
22-30 MAY 2006 |
ARCHAEOLOGY
For the period between 22-30 May 2006, Tom Jones
monitored the crews assigned to remove the concrete floors of the
New Warehouse, CMU Addition, and Grain Warehouse; the footings have
remained in place. For the most part, monitoring was uneventful. A
small number of historic debitage was observed under the floor of
the Grain Warehouse, suggesting the fill may have been an
informal trash pit for placement of unwanted trash and debitage.
The original concrete slab entrance [or exit] of
the northside Grain Warehouse was identified approximately 1-foot
below the modern construction fill (under the CMU Addition). A
portion of this slab was obliterated, but most has been preserved
for recording. Additionally, asphalt remnants and segments have been
exposed under the CMU Addition, indicating the ca. 1960s parking
area evident in archival photographs. While the asphalt may be
modern, it does reveal and expose the original ground level for this
portion of the property, which may also help identify ground levels
for the New Warehouse and Grain Warehouse.
Archaeological trenching and test excavations
will begin 26 June 2006. The prefield logistical tasks will
continue until that time, including production of field forms,
additional mapping of the site, crew assignment, equipment requests,
pre-field meetings regarding the field database being developed,
etc. The kick-off meeting for the entire crew will be held the week
of 19-23 June 2006, where specific field methods will
be discussed with the field crew and all protocols for working at
the site explained.
ARCHIVAL RESEARCH
Kelly Nelson [ACS Document Production Manager]
entered into EndNote the majority of the master Tempe historical
bibliography – she has thus far entered 1,245 of 1,642 bibliographic
entries into the database, providing an extremely useful foundation
for the archival research ACS is conducting for the Hayden Flour
Mill property. Additionally, she is entering all archival research
references gathered by ACS that are not included in the bibliography
provided by Joe. A copy of the complete electronic, searchable
bibliographic database will be provided to Joe Nucci and the City of
Tempe Planning and Development at the end of this project. A copy
can also be provided to the Tempe Historical Museum if they so
desire.
|
|
22 MAY 2006 |
ARCHAEOLOGY
This week, staff documented
the various building episodes evidenced in the concrete pads and
their characteristics. Staff
also worked on total station mapping of them and the rest of
the standing architecture at the site. Feature and unit numbers were
assigned to the different concrete pads. This completes the
pre-field site recording efforts; more in-depth recording and
mapping of the project property will continue throughout the
fieldwork efforts.
On Friday, 19 May 2006, staff
met All Cut at the property and did one final walk through to ensure
that everyone was clear on what areas of the concrete pads are to be
removed and the sequence of work. Concrete removal began
Monday, 22 May 2006 at 6 am.
|
|
5 MAY 2006 |
Press Release
Hayden Flour Mill Archaeology to Begin
|
ABOUT
NEWS
ARCHAEOLOGY
DEVELOPMENT
PRESENTATIONS
PHOTO CONTEST
PHOTOS
LINKS
|