City of Tempe
November 2008 Bond Election

For Spanish copy click here.

Question 1.   Water and Sewer Improvements $113,300,000

91st Avenue Wastewater Treatment Plant

This project represents Tempe's share of all activities at the 91st Avenue Wastewater Treatment Plant (WWTP) including: capacity expansion projects, capital equipment replacement, modifications and additions to meet regulatory requirements, process enhancements, and also capacity expansion of the jointly owned trunk sewer lines that convey wastewater flows to the plant. The 91st Avenue WWTP is a regional treatment facility that is jointly owned by five metropolitan area cities and is operated by the City of Phoenix. The 91st Avenue WWTP comprises the majority of Tempe's wastewater treatment program.

 

Alum Tank Replacement at the South Tempe Water Treatment Plant

This project will install two new bulk Alum storage tanks, related plumbing, and a new top fill system made of stainless steel for unloading safety, at the South Tempe Water Treatment Plant.

 

Central Arizona Project Capital Charge

An agreement with the Central Arizona Water Conservation District imposes a semiannual capital charge payable annually through 2034. These charges repay the federal government's advance of construction funding to build the Central Arizona Project canal system.

 

Distribution System Fittings

This project provides for the acquisition, assembly and installation of water works infrastructure including meters, valves, hydrants and water lines at multiple City locations.

 

Environmental Laboratory Facility

This project will construct a new 10,000 square foot Water Utilities Department, Leadership in Energy and Environmental Design (LEED) Green Building certified Environmental Laboratory facility on existing City-owned land at the South Tempe Water Treatment Plant site adjacent to the existing Environmental Services Building.  10,000 square feet is believed to be sufficient space for all currently required analyses, process control and research analyses, and future requirements added by the Environmental Protection Agency.

 

HVAC Replacement at the Three Water & Wastewater Treatment Plants

This project provides funding to replace city owned air conditioning equipment and carpet located within the three water and wastewater treatment plants that has been identified as being ineffective, inefficient or has exceeded its life span according to the Public Works facility maintenance division. The replacement schedule is as follows:

2008-09: replace 17 heat pumps at the Johnny G. Martinez Water Treatment Plant (JGMWTP), and 3 air conditioning units at the South Tempe Water Treatment Plant (STWTP).

2009-10: replace 14 air conditioning units and heat pumps at JGMWTP, STWTP and Kyrene Water Reclamation Facility (KWRF).

2010-11: replace 1 heat pump and other equipment at JGMWTP, STWTP & KWRF.

2011-12: replace 8 heat pumps and air conditioning units at JGMWTP, STWTP & KWRF.

 

Johnny G. Martinez Water Treatment Plant Capital Equipment Replacement

This project provides an annual funding mechanism to address equipment failures at the Johnny G. Martinez Water Treatment Plant which have not been specifically budgeted. Every year there are unexpected failures of pumps, valves, and other operating equipment due to fatigue, wear, structural failure and many other reasons. Efforts are underway to develop comprehensive preventative maintenance programs and procedures to help minimize equipment failures.

 

Johnny G. Martinez Water Treatment Plant Security Fence - Lighting

This project consists of replacing the existing chain link fence that runs along the western perimeter of the Johnny G. Martinez Water Treatment Plant, and providing perimeter lighting along the same path. The chain link fence currently in place is over 20 years old and is in need of repair. The fence is the only barrier from public access and is not considered to be a high security barrier. The fence will be replaced with a higher level of security fence consisting of solid metal vertical and horizontal materials.  The proposed lighting would consist of free standing poles with lighting fixtures which would illuminate the perimeter fence line. Both the fence and lighting would add another layer of perimeter deterrence and detection for the facility. This project is a continuation of security improvements recommended by a vulnerability assessment completed for our critical assets.

 

Johnny G. Martinez Water Treatment Plant Treatment Upgrades

This project will install additional water quality improvements to meet required water quality regulations at the Johnny G. Martinez Water Treatment Plant. The project includes a comprehensive site study, a Granular Activated Carbon (GAC) facility, and solids handling improvements (plate settlers and sludge holding tank).

 

Ken McDonald Golf Course Recharge Project

This project will address the first two phases of the Tempe Ken McDonald Golf Course Groundwater Recharge Project. Phase 1 consists of deepening and equipping one existing recharge well, to convert it to an Aquifer Storage and Recovery (ASR) injection well. The injection well will provide reclaimed water aquifer storage and recovery. Phase 1 also includes the construction of discharge piping to recover stored reclaimed water (groundwater credits) for delivery to the golf course lakes for irrigation reuse.  Phase 2 includes the drilling and equipping of two additional ASR recharge wells and connection to the discharge piping for irrigation reuse.

 

Kyrene Reclaimed Water Transmission / Distribution Line

With the expansion of the City's Kyrene Reclamation Facility and its producing a higher quality effluent from the use of Membrane Technology, the City has excess reclaimed water to reuse. One major use of this reclaimed water is to refill Tempe Town Lake from evaporation and other losses. In order to accomplish this, a pipeline will be constructed from the Kyrene Reclamation Facility to the Tempe Town Lake. The pipeline will be 24-inch diameter and will be a total length of approximately 5 miles.

 

Kyrene Water Reclamation Facility - Capital Equipment Replacement

This project provides an annual funding mechanism to address equipment failures at the Kyrene Water Reclamation Facility which have not been specifically budgeted. Every year there are unexpected failures of pumps, valves, and other operating equipment due to fatigue, wear, structural failure and many other reasons. Efforts are underway to develop comprehensive preventative maintenance programs and procedures to help minimize equipment failures.

 

Kyrene Water Reclamation Facility - Scum Automation

The scope of this project is to automate the Kyrene Water Reclamation Facility scum gate / drain trough system located at and across all eight membrane basin inlets. The scum gates and piped channel allow cleaning and drainage of excess floatable solids (scum) that accrue at the membrane basin inlets. Potential hazardous gases such as Hydrogen Sulfide are reduced as well. The system now requires excessive operator hours accessing the area, opening difficult valves and hatches, and running water hose lines to allow physical access for spraying and hosing-out the scum troughs once the gate and drain valves are opened properly.  Automating the system at a minimum will require an electrically-controlled gate, a new drain, and sprayer valves with actuators that provide open / close position command and feedback features. Local control panels and conduit and wiring would be added for each valve and sprayer and would include valve status indicators and switches to provide manual or automatic operation of each valve.

Kyrene Water Reclamation Facility - Shade Screen

In order to protect critical equipment at the Kyrene Water Reclamation Facility, shade screening is recommended around the Chemical Storage and Odor Control Scrubber areas. This will protect the scrubber units, recirculation pumps, instrumentation, local control panels, chemical tanks, chemical pumps, piping and associated equipment.  This project will include design and installation of the shade screen.

 

NaOCl Cells and Brine Tank Installation

This project will add two Sodium Hypochlorite (NaOCl) generating cells to the current generating system, and one 60 ton Brine tank to the current NaOCl salt storage system. The addition of the two NaOCl generating cells will reduce system run time during high peak, high demand production times, saving up to 120 hours per month in peak electrical pricing. Adding the additional Brine Tank will help ensure a constant brine supply for NaOCl generation.

 

New Production Well

This project provides funding for one new potable water well, and city connections to four existing wells. The Water Utilities Department Integrated Master Plan (2000), and Water Resources Plan (2006) identified a shortage of well capacity in Tempe and recommend that the City increase well capacity to meet emergency supply needs and supplemental drought supply. These wells would provide an additional 16.5 million gallons per day of production capacity to the City, and coupled with existing wells, meet the needs of an emergency situation. The wells also double as storage capacity and effectively reduce capital requirements for additional aboveground storage and pumping.  The new City of Tempe well is to be drilled and equipped in south Tempe. Two of the four wells to be connected to the City's distribution system will require renovation as part of the project.

 

Scottsdale Road Bio Filter Project

This project will construct a Bio Filter for odor control related to sanitary sewer nuisance odors near the intersection of Scottsdale Road and Gilbert Drive. Public complaints of sanitary sewer odors in the vicinity have recently increased. The project includes site location, and the design and construction of the Bio Filter odor control system.

 

Sedimentation Basins Grout Liner Replacement

This project will completely replace the grout lining in the sedimentation basins at the South Tempe Water Treatment Plant. The current grout in the sedimentation basins is delaminating from the concrete underlayment. The grout serves the purpose of creating an angle for the sludge created from water treatment to collect in the middle of the circular basins for disposal. As the grout separates from the concrete it creates obstacles for the collection racks to overcome and blocks pump impellors and piping.

 

Sewer Line Replacement and Repair

The Water Utility Department Integrated Master Plan (IMP) identifies most of the specific sewer lines that need to be replaced to meet increasing wastewater flows.  This project provides a recurring funding source to replace sewer lines that break during normal operation.

 

Sewer Replacement / Upsize - 5th Street, Price to Smith

This project will replace an estimated 2,650 feet of existing 15 inch sanitary sewer due to insufficient capacity. The new sewer diameter will be 18 inches. The project will alleviate high flow conditions and facilitate Apache Boulevard redevelopment.

 

Sewer Replacement / Upsize - Scottsdale Road, Curry to Gilbert

This project will replace an estimated 1,500 feet of existing 12 inch sanitary sewer due to insufficient capacity. The new sewer diameter will be 15 to 18 inches depending on the location. The project will accommodate additional discharges from the Jonny G. Martinez Water Treatment Facility, and facilitate new condominium development between Weber and Curry.

 

Sewer Replacement / Upsize - Smith Road, Apache to University

This project will replace an estimated 2,670 feet of existing 12 to 15 inch sanitary sewer due to insufficient capacity. The new sewer diameter will be 18 inches. The project will alleviate high flow conditions and facilitate Apache Boulevard redevelopment.

 

South Tempe Water Treatment Plant - Capital Equipment Replacement

This project provides an annual funding mechanism to address equipment failures at the South Tempe Water Treatment Plant which have not been specifically budgeted. Every year there are unexpected failures of pumps, valves, and other operating equipment due to fatigue, wear, structural failure and many other reasons. Efforts are underway to develop comprehensive preventative maintenance programs and procedures to help minimize equipment failures.

 

South Tempe Water Treatment Plant - Security Fence / Lighting

This project would replace the existing chain link perimeter fence that borders the eastern and southern perimeter along the South Tempe Water Treatment Plant.  The project is a continuation of security improvements recommended by the vulnerability assessment completed as per federal requirements.  The existing chain link fence is not considered to be a high level security barrier and does not provide consistent adequate height requirements for security. The fence is also aging and in need of replacement. The replacement fence would be constructed with solid metal vertical and horizontal materials which are consistent with higher security standards. The perimeter fence line adjacent to Price Road would also have a metal cable barrier system installed to prevent vehicular intrusion. The lighting proposed for this site would be of free standing poles with fixtures that would provide sufficient illumination for deterrence and detection of any intruders.

 

South Tempe Water Treatment Plant - Water Quality Improvement

This project includes improvements and modifications to the existing South Tempe Water Treatment Plant that will ensure the plant is in compliance with current water quality regulations and goals. The project includes a Granular Activated Carbon facility and other site improvements.

 

Southern Avenue Interceptor Rehabilitation - All phases

This project funds the phased rehabilitation or the replacement of the Southern Avenue Interceptor (SAI), a jointly owned regional sewer that runs through Tempe.  An engineering condition assessment study revealed severe corrosion of this unlined concrete sewer line, and recommended a phased rehabilitation or replacement of the line to protect it from eventual collapse. This multi-year project addresses all phases of rehabilitation and replacement.

The project will be jointly funded by both Tempe and the City of Mesa. The estimated project costs shown here represent Tempe's portion of full line replacement.

 

Undergrounding of Water Aqueduct at the Johnny G. Martinez Water Treatment Plant

The purpose of this project is to replace the water aqueduct or flume that brings raw water from the Crosscut Canal to the Johnny G. Martinez Water Treatment Plant. The aqueduct is part of the original infrastructure of the plant built almost 45 years ago. The goal of the project is to replace the aqueduct with an underground pipe.

 

Water Line Replacement and Repair

The Water Utility Department Integrated Master Plan identifies most of the specific waterlines that need to be replaced to meet increasing demands. This project provides a recurring funding source to replace water lines that break during normal operation or that have reached their useful life.

 

Water Line Upgrade / Replacement 22nd / 24th Street (Hardy-Roosevelt)

This project will replace approximately 2,520 feet of existing 6 inch cast iron water lines which were installed in 1960. The lines are nearing the end of their design life and do not meet current criteria for providing adequate water supply / fire flow in this heavy industrial area. New fire hydrants, gate valves for additional control, new onsite fire suppression connections, and service meters will be included.

 

Water Line Upgrade / Replacement Margo / Geneva (Fairmont-Hardy)

This project will replace approximately 2,450 feet of existing 6 inch asbestos cement water line installed in 1980. Although the line has only reached its design half-life, it does not meet the current criteria for providing adequate water supply / fire flow in this heavy industrial area. New fire hydrants, gate valves for additional control, onsite fire suppression connections, and service meters will be included.

 

Water Line Upgrade / Replacement Orange / Lemon

This project will replace approximately 3,200 feet of 6 inch water line originally installed in 1962. The existing cast iron line has reached its design life, and does not meet current criteria for providing adequate water supply / fire flow in this multifamily area. New fire hydrants, gate valves for additional control, onsite fire suppression connections, and services meters will be included.

 

Water Line Upgrade / Replacement Rural Road (Rio Salado-Apache)

This project will install approximately 5,000 feet of new 16 inch distribution main water line which will replace the existing 14 inch cast iron pipe on Rural Road between University Drive and Apache Boulevard. The existing 14 inch pipe was installed in 1968 and its now non-standard size makes new connections and repairs more expensive and of longer duration.

The new distribution main will be tied to a larger 30 inch transmission main at Rio Salado, University and Apache. The new line and connections will facilitate the Arizona State University Tempe campus Masterplan, and new development in the Rio Salado corridor. New fire hydrants, gate valves for control, onsite fire suppression system connections, services meters, and connections to the remainder of the distribution system will be included.

 

Well #13 Equipping

Well #13 is located south of the Western Canal between Rural Road and McClintock Drive. This planned well project was originally intended for use as a recovery well project to pump storage credits to the Salt River Project (SRP) canal as a water exchange supply source. The Fiscal Year 2008-09 project scope is being expanded to include a direct connection to the Tempe municipal water distribution system as a back-up drinking water supply well along with the connection to the SRP Western Canal.

 

Question 2.   Street Improvements / Storm Drains $44,200,000

Asphalt Mill and Overlay

This project provides for localized reconstruction and resurfacing of the arterial street system in the City. The majority of the arterial roadways in the City have undergone a number of preventative maintenance applications since originally constructed.  The amount and type of traffic is approaching or has exceeded the design limit of some arterial streets.  By overloading a roadway past its original design, rapid deterioration of the street will result.  By resurfacing and rehabilitating the arterials, the strength and the durability of the roadway will greatly increase while the cost of maintaining the road for the next 10 years will decrease.

 

Baseline Bridge Replacement Over Western Canal

This project will replace the existing Baseline Bridge over the Western Canal.  This bridge was inspected and found to be at the limit of its capacity.

Bridge Maintenance

This project provides for repair and maintenance of bridges located throughout the City.  Federal law mandates the inspection of all bridges in the country every two (2) years.  The Arizona Department of Transportation (ADOT) inspects Tempe's bridges and submits a report to the City for required repairs and maintenance.  The report identifies specific repairs and maintenance required and quantifies the estimated cost to make the repairs.  The City updates these costs for construction inflation and determines current costs.  The scope of work includes replacement of damaged joints, joint seals and diaphragms, cleaning debris out of the joints to allow them to function properly, posting of vertical clearance signs, repair of damaged structural members and guards, replacement of missing bolts and nuts from railings, correction of settlement and subsidence at abutments and miscellaneous other items. This is done to assure that the bridges are safe and in good repair.

 

City Facilities Parking Lots

This project will provide for the sealing, resurfacing and reconstruction of City parking lots in accordance with the City's pavement management program.

 

Design & Install Fiber Optic Communications

This project provides for the development of a communications strategic plan and installation of fiber optic communications along various City roadway corridors.  The fiber optic lines will tie into Arizona Department of Transportation (ADOT) fiber optic infrastructure as the communications media for command and control operations.  The City will be able to monitor and adjust traffic signal timing through centralized command and control strategies designed to help both ADOT and other municipal agencies relieve or minimize congestion.

 

Install Wireless Communications & CCTV Monitoring at 26 Locations

This project will install wireless communications media for command and control operations and closed circuit television monitoring (CCTV) at traffic signals.  Utilizing this city infrastructure will increase communications bandwidth at traffic signals and eliminate the need for existing and new leased telephone service to the intersections.

 

Installation of Pedestrian ITS Devices

The purpose of this project is to convert existing or install new accessible pedestrian devices at traffic signal controlled intersections.  This project is a step toward complying with the Americans with Disabilities Act (ADA) and provides an essential public service for Tempe residents.  Examples of these devices include, but are not limited to, pedestrian crosswalk push buttons, pedestrian countdown signal heads, audible pedestrian technologies and machine vision detections.  These devices provide audible, vibro-tactile and visual information for pedestrians with limited or no hearing or sight.  It improves personal safety as pedestrians navigate Tempe streets.

 

Intersection Reconstruction

This project provides for the reconstruction, resurfacing, and rehabilitation of intersections throughout the City that have been determined to be unsafe for both pedestrian and vehicular traffic.  The project will explore additional pavement alternatives such as portland cement concrete and other additives that will improve the structural integrity of the intersections.  The requested funding will address approximately three intersections per year.

 

Minor Alley Improvements and Dust Control

This project will provide for the improvement of dust control on minor streets and alleys throughout the City, including paving unpaved streets or upgrading substandard minor streets to City standards.  The paving of these streets and dust control in the alleys will assist the City in meeting its air quality standard requirements.  Alleys that have been improved provide an environment that allows the solid waste personnel to complete their duties safely and quickly as well as encourage residents to take ownership of their alley and increase neighborhood pride.

 

Minor Concrete Improvements

This project provides for emergency repair and replacement and new construction of curbs, gutters, and sidewalks throughout the City to improve the continuity of the infrastructure and to improve accessibility and mobility for pedestrians in various areas.

 

Neighborhood Street Rehabilitation

This project provides for the reconstruction, resurfacing, and/or rehabilitation of residential streets in Tempe neighborhoods.  The City's preventive maintenance efforts over the years have preserved the streets and kept them in very good condition.  However, a growing number of residential streets are to the point that preventive maintenance is no longer effective or appropriate.  This program allows for the annual rehabilitation of 6 miles of residential streets on average.

 

Neighborhood Transportation Management

This project will provide the Transportation Division with resources to strengthen its ability to address neighborhood traffic concerns, such as the installation of traffic calming devices, including speed humps.

 

New Signals / Modular Upgrade

This project provides for the installation of new traffic signals and the replacement of existing outdated signals as warranted by traffic engineering studies.

 

Purchase and Install MMU Units in all Traffic Cabinets

This project will allow Tempe to replace its aging malfunction management unit (MMU) inventory with upgraded MMUs.  The upgraded MMUs will provide the City’s signal technicians with enhanced diagnostic tools to troubleshoot intersection malfunctions.  These enhanced capabilities will facilitate increased intersection reliability and ultimately provide for safer traffic control operations.

 

Residential Street Surface Treatments

This project will provide the ongoing preventative maintenance (slurry seal) of local / residential streets throughout the City in accordance with the City's pavement management program.

 

Storm Drain Improvements

This project provides for the construction of minor storm drain extensions, and equipment replacement and upgrades, to relieve localized problems associated with various storm water retention facilities.

 

Street Light Pole Structural Replacement

The project will fund the replacement of all rusted direct buried street light poles to meet current street light pole foundation standards.  It is estimated that there may be 3,000 rusted street light poles in the City's inventory which may increase because of corrosion over the next ten years.

 

Street Light Upgrades / New Installation

This project provides for the installation of new street lights at various locations as well as the upgrading of street lights from mercury vapor luminaires to high pressure luminaires.  A typical year's program would include installation of 100 new arterial street lights and 25 mid-block residential lights.

 

Street Microsurfacing

This project provides ongoing preventive maintenance and resurfacing of major arterial and collector streets throughout the City in accordance with the City's pavement management program. Without routine maintenance, the arterial street network in the City will decline at a rapid rate.

 

Street Reconstruction and Improvements

This project provides for the reconstruction, resurfacing, and rehabilitation of isolated and/or small groups of streets that have exceeded their design life or that were never part of the City's street system.  Streets and/or public rights-of-way in this category include streets that were acquired through the annexation process throughout the years, and streets/rights-of-way that have never been constructed to City standards.

 

Utility Undergrounding

This project will provide for the undergrounding of overhead utility lines.  Tempe City Code requires the undergrounding of all new and existing utility lines in conjunction with a development/redevelopment project.  However, in established residential areas, the possibility of undergrounding being done by others (or developers) is unlikely.  Therefore, the City budgets for the undergrounding of these areas to provide a more reliable power source as well as aesthetics.

 

Video Traffic Detection

This project will utilize video detection and Closed Circuit Television (CCTV) monitoring at arterial traffic signals to obtain real-time, 24 hours per day, 7 days per week turning movement count data.  Utilizing the video detection equipment will also assist in better managing arterial operations due to the video that is provided by the video detection device.  The City will be able to adjust traffic signal timing through centralized command and control strategies designed to help relieve or minimize congestion.

 

Question 3.   Public Safety $32,010,000

Fire Station 2

This project will construct a new four bay fire station on south Hardy Road where the existing Fire Station 2 and the Support Services Facility are currently located.  The project will entail the demolition of both the existing Fire Station 2 and the Support Services Facility; therefore the commencement of this project is dependent on prior completion of the New Support Services Facility project.  Completion of the new Fire Station 2 will resolve the station’s current lack of space and accommodate an additional fire vehicle.

 

Laptop Replacement

This project provides for the replacement of ruggedized laptop computers used by Patrol Officers and other field personnel.

 

New Support Services Facility

This project will construct a new Support Services Facility for the Fire Department.  The existing facility is inadequate in terms of size and capabilities.  The project will include purchase of land for the facility, and the new facility will house the department’s primary maintenance and warehouse areas. The facility will include expanded room for the department’s vehicle maintenance and parts storage, welding area, work space, test space, and cleaning area.  The facility will also house the department’s primary reserve apparatus; a pumper truck and a ladder truck.  These vehicles need to be kept in a fully ready state, including all equipment, and must be kept in a secure location.  The warehouse area alone will be approximately 5,000 square feet.

 

Police/City Radio System Replacement

This ongoing project provides for the replacement of outdated radio equipment for the Police Department and other City radio users and allows Tempe to participate in the establishment of long term public safety interoperability in the Phoenix metro area.

 

Radio Replacement for Conversion to 800 Megahertz

This project provides additional funding for the fire department’s federally mandated conversion to 800 MHz radios.  Funding will allow the department to complete the conversion and remain on track in its partnership with the other metropolitan area cities in the Automatic Aide System.

 

Renovation of 120 East 5th Street Facility

The purpose of this project is to renovate portions of the first and second floor of the facility located at 120 E. 5th Street to provide adequate work space for employees assigned to the Police Department and the Information Technology Department.  The Police Department plans to relocate the Special Services/Downtown Bike area from an existing trailer and move the Hiring and Recruitment function to the first floor for better public access.  The proposed renovations would redesign inefficient workspace configurations, bring the facility into ADA compliance, address environmental and safety issues such as an antiquated Halon fire suppression system, and upgrade the fire alarm system.  The renovation will also resolve a drainage problem which has previously resulted in flooding of portions of the facility and will provide for energy efficient lighting.

 

Replace Burn Room at the Fire Training Center

This project will renovate and modernize the existing fire training burn room at the Fire Training Center which was built in 1993.  The existing burn room is used on average 41 days per year for fire training and sustains damage with each live fire training which limits the life of the building. The burn room is a critical training area for firefighter safety.

 

TIPS (Technology Integrated Police Systems)

The Technologically Integrated Police Systems (TIPS) project provides the necessary resources to incorporate new technology in the Police Department, as well as resources to upgrade and interface existing automated systems. Planned projects include the implementation of Police specific GIS layers, computer based training applications, continued development of the wireless infrastructure, hardware for growing data storage needs, replacement of printers and other specialty hardware, and upgrades to software. Funding for this project also provides for the initial setup costs of COPLINK, a regional web-based data sharing and crime trend analysis software that will link with the crime records databases from neighboring municipal agencies.

 

Question 4.   Park Improvements/Community Services $51,800,000

Athletic Field Lighting Improvements

This project upgrades the lighting levels at all deficient baseball, softball and multipurpose athletic fields so that they are in compliance with Illuminating Engineering Society recommendations.

 

Diablo Stadium Scoreboard Replacement

This project provides funding for the replacement of the existing scoreboard at Diablo Stadium.  This project will also replace the scoreboard’s operating system.  The existing scoreboard has been in service for more than thirty years.

 

Kiwanis Park Sprinkler System Replacement

This project provides for the replacement of the sprinkler system in Kiwanis Park.  The project includes the installation of new 6 inch water mains, valves, lateral lines, and heads and controllers.  The project will also include dedicated irrigation to park trees which is not present with the existing system.  Construction will be done in two phases over a two year period.

 

Neighborhood Park Improvements

This ongoing project provides for the replacement of playground equipment, picnic equipment, fencing, signage, concrete, sand, rubber playground surfacing, etc. in the City's various neighborhood parks.

 

Park Renovation and Restoration

This project will fund the renovation of three neighborhood parks per year.  The project incorporates a planning process involving extensive neighborhood input.  Renovations will involve improvements to playgrounds, irrigation systems, electrical and lighting systems, picnic facilities, landscaping, and accessibility.  The project also includes renovations and upgrades to various park restrooms, renovation of the Kiwanis Park Recreation Center wave making equipment, rehabilitation of the Kiwanis Recreation Center, restoration of Escalante Swimming Pool amenities, and replacement of the Kiwanis Park Batting Range netting.

 

Sports Facility Relamping

This project provides for the continued funding of a maintenance program for the City’s sports facilities lighting needs.  The project establishes a plan for a regular cycle of relamping and cleaning of light fixtures at all softball/baseball fields, soccer fields, tennis and racquetball courts and park basketball and volleyball courts.

 

Street Landscaping

This ongoing project provides funding for tree maintenance and replacement, irrigation, and other landscaping in various street rights-of-way and public properties.

 

Tempe Historical Museum Renovation Project

Funding for this project will complete the renovation of the 8,000 square foot exhibit hall and gallery, and related amenities in the Tempe Historical Museum.  The project also provides approximately 4,000 additional square feet of storage space and provides necessary upgrades to the existing fabrication workshop.  The project will also address significant necessary HVAC repairs.