Bid Results

Print

Click on the Engineering project name below for results of the bid opening:

Bid results are posted as soon as possible once they are approved. If the results are not listed yet, please check back again. 

 

Sports Field Lighting Replacement - Corbell Park, Project No. 6303081C
Bids currently being reviewed for approval.  The apparent low bidder is AJP Electric, Inc.


Street Preservation - Mill Avenue from Southern Avenue to Broadway Road and Bell De Mar Drive from Rural Road to Terrace Road, Project No. 5499741F.
Bids currently being reviewed for approval. The apparent low bidder is Lincoln Constructors, Inc.

 

Street Preservation - Neighborhood Bound by US 60 and Southern Avenue; McClintock Drive and Price Road, Project No. 5499741G.  Recommend contract award to Sunland Inc. Asphalt & Sealcoating on March 23, 2017.

Restroom Building Replacement - Daley Park, Project No. 6307631B
Recommend contract award to LAM Industries, LLC., on February 23, 2017.
 

Railroad Crossing Safety Improvements - Union Pacific Railroad at Broadway Road, Project No. 5405381
Recommend contract award to AJP Electric, Inc., on January 26, 2017.  AJP Electric, Inc. was found to be the low, responsive bidder.


Intersection Improvements - Rural Road and Tyler Street/ Terrace Road, Project No. 6907741
Recommend contract award to AJP Electric, Inc., on January 12, 2017.

 
Storm Water Pump Station Improvements - Hanger Park, Project No. 3207841
Contract awarded to Spectra Electrical Services, Inc. on December 8, 2016.
 

Demolition - Apache Boulevard and River Drive - Northwest Corner, Project No. 6700106
Contract awarded to to Breinholt Contracting, Co.  


Traffic Signal Foundations 2016-2017, Project No. 6903385
Contract awarded to B & F Contracting, Inc. on December 8, 2016.
 

Renovation and Infrastructure Improvements - McClintock Swimming Pool, Project No. 6307951
Contract awarded to Sun Eagle Corporation on October 27, 2016.

Flood Irrigation Infrastructure Improvements - CIPP Lining - 9th Street to 13th Street Alley West of Mill Avenue, Project No. 3205891B
Contract awarded to Insituform Technologies, LLC. on September 8, 2016.

 

Rio Salado Multi-use Path - Priest Drive Underpass, Project No. 6007181
Contract awarded to Briston Construction on September 8, 2016.

 

Street Resurfacing - Warner Road from Kyrene Road to I-10, Project No. 5499741D
Contract awarded to Nesbitt Contracting Co., Inc. on August 4, 2016.

 

Minor Concrete Improvements 2016/2017, Project No. 5407971
Contract awarded to R.K. Sanders, Inc. on August 4, 2016.

 

Street Resurfacing - Guadalupe Road from East to West City Limits and Dorsey lane from University Drive to 8th Street, Project No. 5499741
Contract awarded to Sunland, Inc. Asphalt & Sealcoating on June 23, 2016.

 

Kyrene Multi-Use Path Canal Fence, Project No. 6005423
There were no bids received for this project.

Flood Irrigation System Infrastructure Improvements - CIPP Lining College Avenue Segment, Project No. 3205891
Contract award to Insituform Technologies, LLC. on May 26, 2016
 

CNG Dispensing System Expansion - Public Works Department Fuel Yard, Project No. 6705181A
Contract award to RKS Plumbing & Mechanical, Inc. on April 14, 2016.

Control, Air Monitoring and HVAC Improvements - East Valley Bus Operations & Maintenance Facility, Project No. 6006083
Contract award to D.L. Withers Construction, LC on March 17, 2016

 

Park Infrastructure Improvements - Escalante Park, Project No. 6307921
Contract award to AJP Electric, Inc. on January 28, 2016.