TARGET Turn Around Times

 

Please note:  These are target turn around times only and may change due to

 

workload, staffing considerations,  and size or complexity of project.  

 

Type of Plan Review

Initial Plan Review
Working Days 
Re-submittals
Working Days
New Commercial -
> $10 million valuation
Negotiated > 20 > 10
New Commercial -
< or = $10 million valuation
20 10
Additions/Alterations
(time dependent upon scope of work)
15-20 8-10
Tenant Improvements

> $500,000

12 8
Tenant Improvements

< $500,000

8 6
Other 8 6
AFES 8 4
MEP only 8 4
Residential 8 6
Fire 6 4
Revisions  4 4
Engineering
(commercial/multifamily)
20

1st re-submittal 10 days

All subsequent re-submittals 5 days

Engineering (residential) 8 6

For questions about Target Turn Around Times, contact:

 

Roger Vermillion
Plan Review Administrator
roger_vermillion@tempe.gov
480.350.8071

 

Lisa Loyd
Development Project Coordinator
lisa_loyd@tempe.gov
480.350.8644