Types of permits vary
depending on the type of work being done. If you have any questions about
the the type of permit required for your project, please call (480) 350-8341,
Option 2.
-
Building Permit Required for most tenant improvements and building construction work, including fences
over 6 feet in height
and accessory/storage buildings over 120 square feet. A
Project Submittal Form and 3 complete sets of plans are required for
Commercial and Industrial submittals. A
Project Submittal Form and 2 complete sets of plans are required for
Residential submittals. Plan review and Permit Fees vary.
-
Mechanical Permit Required to alter, repair or add any mechanical equipment such as vent fans,
evap coolers, refrigeration systems, furnaces or incinerators. A
Project Submittal Form and 2 sets of plans are required for
submittal. Plan review and Permit Fees vary.
-
Electrical Permit Required for any electrical wiring work such as new or additional branch
circuits, installing or changing out service entrance section, special event
generators, or temporary construction power. A
Project Submittal Form and 2 sets of plans are required for
submittal. Plan review and Permit Fees vary.
-
Plumbing Permit Required to alter, repair or add any plumbing such as new or replacement
fixtures, water or gas piping, water heaters, sewer, sprinklers or backflow
devices. A
Project Submittal Form and 2 sets of plans are required for
submittal. Plan review and Permit Fees vary.
-
Zoning or Mobile Home
Permit Required to install new or relocated Mobile Homes. Fee is $50.00
and is issued over the counter. A separate building permit may be
required for awnings and carports. A
Project Submittal Form and 2 sets of plans are required for
submittal.
-
On-Site Permit Required for new or relocated Factory Built Buildings (ICBO approved).
A
Project Submittal Form and 2 sets of plans are required for
submittal. Plan review and Permit Fees vary.
-
AFES or Fire Sprinkler
Permit Will be issued under the Building Permit but must be submitted
separately. A
Project Submittal Form and 2 sets of plans are required for
submittal. Plan review and Permit Fees vary.
-
Foundation Only Permit
Contact Plan Checker or Plan Check Manager.
-
Grading Only Permit
Issued at the customer's request only after a Building
Permit has been applied for. A
Project Submittal form, 2 sets of grading plans, Soil
Investigation Report and Permit Fees are
required for submittal.
- Demolition Permit
Required for the removal of permanent building elements (interior walls,
floors, ceiling, doors, windows, etc.) A
Project Submittal, 2 sets of
plans and a building and Permit Fees are required for submittal as a Tenant Improvement.
Please note:
The building permit required for the removal of an entire building
can be
issued over the counter with a project submittal, a site plan and a building
permit fee.
|