|
|
|
|
|
Phoenix Sky Harbor - City of
Tempe History
|
|
|
1935
|
City of Phoenix purchased the airport
from the private carrier for
$35,300 cash and a
$64,700 mortgage. |







 |
|
1947
|
Airport Master Plan
recommended expansion from one to three runways (east/west,
north/south and diagonal). |
|
1952
|
Terminal 1 was constructed at a cost of
$850,000. The three runways provided for a total number of
operations that made Phoenix the 11th busiest airport in the nation. |
|
1959
|
Airport Master Plan called for the
elimination of the diagonal runway to allow for more terminal space. |
|
1962
|
Terminal 2 (formerly called East
Terminal) was developed at a cost of $4.1 million. An outdoor
walkway was added to allow passengers walk to and from their
aircraft. |
|
1970
|
Concerned citizens formed the Tempe
Environmental Improvement Committee (TEIC) in response to massive
citizen complaints about the noise of commercial aircraft
over-flights of their neighborhoods. |
|
1972
|
Airport
Master Plan called for a relocation of the Air National Guard and
re-canalization of the Salt River to accommodate a 3rd runway. |
|
1973
|
Recommended “Noise Abatement and
Operative Procedures” were approved and released by the City of
Phoenix Aviation Director. Aircraft were directed to avoid developed
residential areas to the east both north and south of the
Salt River. |
|
1974
|
The Rio Salado Radio
Beacon was installed as a navigational aid to keep departing
aircraft over the “river route.” |
|
1977 |
A 181 foot tall tower
adjacent a new Terminal 3 replaced the 60 foot tall tower at Cutter
Aviation built in 1956. |
|
1979
|
Terminal 3 was opened. Heavy
flooding from the Salt River during the late 1970's did not close
the airport although parts of the runways were under water. Terminal
3 accommodated additional flights including Boeing 727’s and 707’s. |
|
1980
|
Tempe City Council
appointed the Tempe Aircraft Noise Abatement Committee (ANACOM) to
make policy recommendations to the Council on noise generated by
airport operations. |
|
1981
|
ANACOM submitted a report to Tempe City
Council noting that noise would increase due to recent deregulation,
deviations from flight patterns and expansion of the airport that
included a third runway proposed in the PRC Speas Master Plan
Update. |
|
1983
|
The Phoenix City
Council approved the airport Master Plan and the City of Phoenix
committed in writing to Tempe that if a third runway was
constructed it would be used for general aviation only. The plan
called for relocation of the 2nd runway and a new 3rd parallel runway to be
constructed with a minimum 800-foot spacing between the two. This
would satisfy the minimum requirement of 4.300 feet between the
north and new 3rd runway centerlines to conduct parallel approaches. |
|
1985
|
City of Tempe
received an Aircraft Noise Mitigation Study from hired consultant
Michael Bradman Associates. The consultant recommended that the City
requested modifications to the airport's flight paths and departure
distributions to protect property in the City of Tempe. A revised terminal
development plan was prepared by the
City of Phoenix Aviation Department, which evaluated
various concourse schemes for a new pier centralized terminal, which
was materialized with construction of Terminal 4. |
|
1988
|
Airport Master Plan
Update called for the construction of Terminal 4, demolition of
Terminal 1 and adding a 3rd parallel runway. The total cost of this
plan, including the relocation of the Air National Guard and the
realignment of 24th Street was estimated to be about $160 million.
|
|
1989
|
A FAR Part 150 Noise Compatibility Study
was completed for the airport. The study included assumptions of
added impacts because of improvements proposed in the 1988/89 Master
Plan. |
|
1990
|
Terminal 4
(Barry Goldwater
Terminal) was built for $250 million.
America West Airlines, Southwest
Airlines, the PHX Tower/TRACON signed a letter of agreement on the 1
DME Standard Instrument Departure procedure (SID) to the east
established for noise mitigation purposes. |
|
1991
|
FAA released a Draft Environmental
Impact Statement (DEIS) for the airport Master Plan Update and
conducted public hearing meetings. The City of Tempe submitted
extensive comment on the
draft
alleging serious flaws in assumptions on environmental impacts and
proposed noise mitigation measures.
|
|
1992
|
A navigational aid, the
Salt River VORTAC, was moved to make way for ADOT's freeway project.
The FAA made changes to the SID, the "1-DME" became the "4-DME"
procedure. The City of Phoenix Aviation Director notified the City
of Tempe on a change in the east departure heading off the north
runway from 90 to 85 degrees to intercept the 75 degree radial off
the relocated VORTAC. |
|
1993
|
FAA issued the Final
Environmental Impact Statement (FEIS) for projects included in the
airport Master Plan Update. |
|
1994
|
The FAA
issued a Record of Decision (ROD)
approving the Maser Plan projects.
The City of Tempe filed law suits against the FAA and
the Environmental Protection Agency over the FEIS. The City of Tempe
agreed to a request by U.S. Court of Appeals, 9th Circuit, to try
settle the suits through mediation, and as a result the City of
Tempe accepted that the suits were dismissed by the Court provided
that the FAA amended the ROD to reaffirm commitments to uphold noise
mitigation flight procedures over Tempe. The City of Tempe and the
City of Phoenix made an Intergovernmental Agreement (IGA) on noise
mitigation flight procedures to be upheld and the implementation of
a new procedure proposed in the FEIS to mitigate noise impacts from
large aircraft that would be landing on the proposed 3rd runway. The
City of Phoenix agreed to install a
Noise and Flight Track Monitoring System
(NFTMS) for the airport and update the FAR Part 150 Study from 1989.
The FAA issued an amendment to the ROD. |
|
1995
|
The City of Tempe
established the Tempe Aviation Commission (TAVCO) consisting of
appointed residents from aircraft noise impacted areas in the City
to assist and advise the Mayor and City Council on aircraft noise
impacts, the implementation of the 1994 IGA, and other related
issues. TAVCO replaced ANACOM.
TRACOR Applied Sciences Inc. was hired
by the City of Phoenix to install a Noise and Flight Track
Monitoring System (NFTMS) for the airport. |
|
1997
|
The City of Phoenix
Aviation Department rejected an NFTMS "Corridor"-measure to monitor
airline compliance with the 4-DME noise mitigation flight procedure
based on existing SIDs that was proposed by TAVCO and endorsed by
the Tempe City Council in 1996. The Aviation Department implemented
an NFTMS "Gate" at 4-DME to identify airlines that would receive
notifications for not complying with the 4-DME instrument departure
procedure. |
|
1999
|
TAVCO got City Council
approval for conducting a study of public perception of aircraft
noise in Tempe. Dr. Bruce Merrill concluded that aircraft
noise was primarily a problem north of Apache Boulevard with basis
in survey data collected in November and December 1999. After the
FAA conducted an airport inspection pointing to the wildlife hazard
due to run-off from the Tempe Town Lake, the City of Tempe
reaffirmed its commitment to implement measures that would prevent
wild life habitats in the Salt River areas of the Town Lake to the
FAA. |
|
2000
|
3rd runway inaugural
flights took place on October 5th, but after a few flights the
runway was temporarily closed for completion of work on runway
lights. TAVCO got City Council approval for conducting the second
part of the noise perception study. The City of Phoenix Aviation
Department submitted and update to the 1989 study as stipulated in
the 1994 IGA. |
|
2001
|
Dr. Bruce Merrill
presented survey results to TAVCO indicating that Tempe
residents were generally more aware of the aircraft noise compared
to 1999, and that the problem is getting worse in all areas
surveyed. The FAA canceled the SIDs in exchange for RADAR vector
DP's formalizing procedure changes to phase in the third runway. The
City of Tempe petitioned the U.S. District Court for the District of
Columbia to review actions taken by the FAA in incorporating changes
to the departure procedures to the east including those proposed in
the NW 2000 re-routing Plan.
The FAA
approved the
2000 FAR Part 150 update, which included noise mitigation measures
agreed upon in the 1994 IGA. The Arizona Tourism and Sports
Authority submitted plans for a stadium in Tempe to the FAA that
later resulted in a determination of Hazard to Air Navigation by the
FAA's Western Pacific Regional Office. URS Corporation conducted a
public meeting on the scoping of the Environmental Impact Statement
of proposed improvement projects at the airport that included
construction of a new west terminal. |
|
2002
|
The FAA suspended implementation of a
side-step
visual approach procedure to the third runway after receiving flight
safety warnings from NATCA and airline representatives, and after an
attempt to formalize the procedure failed. The FAA issued a
Draft Environmental Assessment for proposed construction and
operation of a new ATCT/TRACON facility just east of Terminal 3 with
a 320 foot tall tower. The City of
Tempe petitioned the U.S. District Court for the District of
Columbia to enjoin the FAA from funding and the City of Phoenix from
proceeding with the reconstruction of the center runway, alleging
Clean Air Act violations. The City of Tempe’s request for injunction
was denied. |
|
2004
|
The Tempe City Council
agreed to settle petition over miscellaneous departure procedures
for the consideration that the FAA would notify the City of Tempe
through the Phoenix Airspace Users Working Group (PAUWG) of
intentions to make changes to flight procedures. A draft
Environmental Assessment (EA) was issued on stage 1 of a proposed
Automated People Mover (APM) project at the airport. |
|
2005
|
The FAA issued a Draft
Environmental Impact Statement (DEIS) for miscellaneous proposed
construction projects at the airport including a new 33 gates west
terminal complex, stage 2 of the APM, cross-field taxiways, and
modifications to Sky Harbor Boulevard. TAVCO called a special
meeting for residents to comment on the draft prior to URS public
meetings, and recommended the City ask for an extension of the
public comment period, which was done by the FAA upon request from
the City of Tempe. |
|
2006
|
The FAA issued a Final Environmental
Impact Statement (FEIS) for the proposed construction projects and
an ROD approving the projects. The City of Phoenix Aviation
department got the Phoenix City Council to enact a proposed
amendment to the City's airport height zoning ordinance.
The amendment changed the
allowable building heights within a Phoenix “Downtown Zone” that
included the boundaries of 7th Avenue to 7th Street and Fillmore
Street to Lincoln Street. |
|
|
|
|